DESIGN OF MARTAPURA RIVER BRIDGE STRUCTURE, BANJAR REGENCY

Markawie Markawie, Teguh Prastiyo

Abstract


The Martapura River Bridge is located on Jalan A. Yani KM 40 Martapura, Banjar Regency, South Kalimantan. Traffic processes that occur on Jalan A. Yani KM 40 Martapura often experience problems because congestion often occurs and the condition of the old IA bridge sometimes makes driving users feel restless when crossing the bridge located on the Martapura river. So that at the location of the Martapura river, it is deemed necessary to build a bridge next to the IA bridge so that the IB bridge to be built can be more sturdy and durable so that there is no anxiety for driving users and also to reduce congestion that occurs, where later the IB bridge will be used as a road with one way only towards Banjarmasin and the martapura IA bridge will be used as a one-way road towards the Hulu Sungai so that it will make it easier for traffic on Jalan A. Yani KM 40 Martapura.
The methodology used in loading planning refers to SNI 1725-2016 concerning Loading Standards for Bridges. For the methodology in calculating the stress loss, refer to the NAASRA Bridge Design Specification on Chapter VI Bridge Design Specifications (Prestressed Concrete Design). For the methodology in calculating the moment of the vehicle floor using the Three Moment Equation method and for the method of subsidence of group pile foundations using the method of Schultze and Sheriff (1973), assuming that the pile group is the Equivalent Raft Foundation. The material used in the design of the upper structure is prestressed concrete, while the lower structure is planned to use reinforced concrete with a square pile.
The results obtained are the T-Girder Prestressed type bridge with class A, 34 m span, 7 m traffic width, and 1 m wide sidewalk. Prestressed T-Girder is designed using fc' 40 MPa (K-482) Strands used are uncoated 7 wire super strands ASTM A-416 grade 270 with a diameter of 12.7 mm and an area of 100 mm2 with a tensile strength of 1860 MPa. As for the lower structure, the abutment uses concrete with a quality of fc' 25 MPa (K-300) with a height of 565 cm, a width of 480 cm and a length of 1050 cm.type piles Square Pile with a length of 15 m with a quality of 50 MPa (K-600) with a width of 60x60 cm with a configuration of 18 piles for each abutment. Estimated Budget Plan The cost of constructing the Martapura river bridge is IDR 8,129.511,475.00.-.

Keywords


Bridge, T-Girder Prestressed, Square Pile

References


Arief, Saifuddin. "Slope Stability Analysis with Slice Method". Unpublished compilation book (2008).

National Standardization Body. (2004). Design of Concrete Structures for Bridges (RSNI T-12-2004). Jakarta: National Standardization Agency.

National Standardization Body. (2015). Specifications for structural steel buildings (SNI 1729-2015). Jakarta: National Standardization Agency.

National Standardization Body. (2019). Structural concrete requirements for buildings (SNI 2847-2019). Jakarta: National Standardization Agency.

National Standardization Body. (2017). Geotechnical Planning Requirements (SNI 8460 2017). Jakarta: National Standardization Agency.

National Standardization Body. (2016). Loading Standards for Bridges (SNI 1725-2016). Jakarta: National Standardization Agency.

National Standardization Body. (2016). Earthquake Resistance Planning Standards for Bridges (SNI 2833:2016). Jakarta: National Standardization Agency.

National Standardization Body. (2008). Field Penetration Test Method With SPT (SNI 4153:2008). Jakarta: National Standardization Agency.

National Standardization Body. (2008). Specification for Plain Type and Layered Elastomeric Bearings for Bridge Laying (SNI 3967-2008). Jakarta: National Standardization Agency.

Das, Braja M., Noor Endah Mochtar, Indrasurya B. Mochtar. (1995). Soil Mechanics (Principles of Geotechnical Engineering). Surabaya: Erlangga Publisher.

Hardiyatmo, Hary C. (1996). Foundation Techniques 1 & 2. Jakarta: Publisher PT Gramedia Pustaka Utama.

Ministry of Public Works of the Republic of Indonesia with the Australian International Development Assistance Bureau. (1992). Bridge Design Manual: Volumes 1 & 2.

Ministry of Public Works and Public Housing. (2015). Guidelines for General Requirements for Bridge Design: No. 07/SE/M/2015. Jakarta: Ministry of Public Works and Public Housing.

Soil Mechanics Laboratory. (2021). Final Report on the Design of the Biawan-2 River Bridge Structure PT. Lifere Agro Kapuas, Kapuas Regency, Central Kalimantan Province. Banjarbaru: Faculty of Engineering, University of Lambung Mangkurat.

UPT Library. (2018). Final report Planning of Pondok Nongko Banyuwangi Bridge Using Box Girder Jember Regency, East Java Province. Jember: Faculty of Engineering, University of Jember.

National Association Of Australian State Road Authorities (1976). NAASRA Bridge Design Specification.

Directorate of Road Program Development, Directorate General of Highways, Ministry of Public Works.Prestressed Concrete Bridge Superstructure Standard (Type T-Class A). Jakarta: Directorate of Road Program Development, Directorate General of Highways, Ministry of Public Works.

Ilham, MN (2008). Calculation of Prestressed Beams (PCI Girder). Yogyakarta.

Sardjono, HS. (1988). Pile Foundation Volume I & II. Surabaya: Sinar Wijaya Setiawan Publishers, Agus. (2016).

Design of Reinforced Concrete Structures Based on SNI 2847:2013 (Based on SNI 03-1729-2002). Jakarta: Erlangga Publisher.

Sunggono. (1984). Civil Engineering Book. Bandung: Nova.

Supriyadi, Bambang and Agus Setyo Muntohar. (2007). Bridge. Yogyakarta: Beta Offset.




DOI: http://dx.doi.org/10.20527/infotek.v23i2.15555

Refbacks

  • There are currently no refbacks.


Copyright (c) 2022 INFO-TEKNIK