ANALISIS PERCEPATAN PROYEK DENGAN METODE CRASHING PADA PEMBANGUNAN RUMAH KOMERSIL (STUDI KASUS : PROYEK PEMBANGUNAN 3 UNIT RUMAH TIPE 45 NEW AIYANA 2025, PALANGKA RAYA)

KEVIN FANI KRISTIAN

Abstract


Delays in construction projects are a recurring issue in Indonesia, often resulting in budget overruns and reduced efficiency. This study analyzes a project acceleration strategy using the crashing method on a housing project consisting of three Type 45 residential units located in Palangka Raya, Central Kalimantan. The project was originally scheduled for 214 calendar days, with a contract value of Rp 557,639,742.03. Despite the relatively small scope, time constraints and a client request for faster delivery required optimization efforts.
By applying descriptive quantitative methods, this research evaluated two crashing alternatives: adding working hours (overtime) and increasing labor. The study reviewed previous implementations of crashing methods and assessed their relevance to this case. Results show that accelerating the critical path can reduce project duration effectively while maintaining cost efficiency.
The results of the crashing analysis using two alternatives—1-hour and 2-hour overtime additions—were compared based on efficiency in the crash activity of Batako Wall Installation (1PC:3PP). Between the two alternatives, the 2-hour overtime option was selected due to its higher time efficiency and negligible difference in cost efficiency compared to the 1-hour alternative. The 2-hour overtime alternative proved more effective given the significant reduction in overall project duration. It shortened the project by 6 days, from 215 calendar days to 209 days—resulting in a 2.7% time efficiency. The total project cost was reduced by Rp 3,597,896.45, from Rp 633,800,000.00 to Rp 630,202,103.55, yielding a 0.56% cost efficiency.

Keywords


Commercial Housing, Crashing Method, Overtime, Additional Labor.

Full Text:

PDF

References


Armalisa, A., & Triana, D. (2020). Metode Crashing Terhadap Penambahan Jam Kerja Optimum pada Proyek Konstruksi. Jurnal Teknik Sipil Universitas Serang Raya, 1–18.

Djau, M. F. M., Arsjad, T. T., & Inkiriwang, R. L. (2021). Percepatan Pelaksanaan Proyek Dengan Penambahan Tenaga Kerja Pada Pembangunan Ruko Di Jalan Bukit Moria, Tikala Baru. Jurnal Sipil Statik, 9(4), 709–716. https://ejournal.unsrat.ac.id

Ervianto, W. (2023). MANAJEMEN PROYEK KONSTRUKSI. Andi. https://books.google.co.id/books?hl=en&lr=&id=jHLDEAAAQBAJ&oi=fnd&pg=PP1&dq=info:e5ixChdeaHcJ:scholar.google.com&ots=RbllRDxPVj&sig=-wLMXmL-hF-e2i4IWC6ouGG9RBs&redir_esc=y#v=onepage&q&f=false

Hayati, N. I., & Lugi, D. (n.d.). EVALUASI BIAYA DAN WAKTU DENGAN METODE EARNED VALUE MANAGEMENT (Studi Kasus: Ruko Damara Village, Kel. Ciparigi, Kota Bogor). Jurnal Komposit, 4(2).

Jurnal Percepatan. (n.d.).

Olivia, P. (2019). Analisa Percepatan Waktu Proyek Menggunakan Metode Crashing (Studi Kasus: Peningkatan Jalan Pelantaran - Parenggean - Tumbang Sungai). JurnalTeknika, 3(1), 41–52.

Salakory, N. C., Jamlaay, O., & Titaley, H. D. (2023). Program Dan Fast-Track. Analisa Percepatan Waktu Pada Proyek Pembangunan Struktur Gedung Laboratorium Unpatti Mengunakan Metode Crashing Program Dan Fast-Track, 2(1), 29–39.

Saputra, N., Handayani, E., & Dwiretnani, A. (2021). Analisa Penjadwalan Proyek dengan Metode Critical Path Method (CPM) Studi Kasus Pembangunan Gedung Rawat Inap RSUD Abdul Manap Kota Jambi. Jurnal Talenta Sipil, 4(1), 44. https://doi.org/10.33087/talentasipil.v4i1.48

Soviana, W., Herlina, E., Soviati, S., & Musrian, A. (2022). Identifikasi Faktor-Faktor Penyebab Cost Overrun dan Time Overrun pada Proyek Konstruksi Gedung. Tameh: Journal of Civil Engineering, 11(1), 11–20. https://doi.org/10.37598/tameh.v11i1.156

Keputusan Menteri Tenaga Kerja dan Transmigrasi Republik Indonesia. Nomor Kep.102/MEN/VI/2004. Waktu Kerja Lembur dan Upah Kerja Lembur.




DOI: http://dx.doi.org/10.20527/infotek.v26i2.23258

Article Metrics

Abstract view : 28 times
PDF - 10 times

Refbacks

  • There are currently no refbacks.


Copyright (c) 2025 INFO-TEKNIK