SCHEDULING ANALYSIS OF PLAN, REALISATION, AND ESTIMATION BY USING PRECEDENCE DIAGRAM METHOD (PDM) (CASE STUDY : CONSTRUCTION DEVELOPMENT PROJECT MULTI-PURPOSE SPORTS HALL PHASE IV IN KATINGAN REGENCY)
Abstract
In its implementation, starting from planning, scheduling implementation, to supervision and implementation of controls properly, construction projects have a complicated and dependent series at each stage. In the process of Construction of Phase IV Multipurpose Sports Building located in Katingan Regency, there were delays due to several obstacles. This is related to time management, thus affecting the delay in project completion. This study aims to analyse the difference in the period of delay that occurs based on the scheduling plan, realisation, and estimation with the help of Microsoft Project 2021, as well as identifying the critical and non-critical path of work on the three schedules. In this study, the quantitative analysis method, where data collection was carried out by interviewing and distributing questionnaires to several respondents from Supervisory Consultants and distribution of questionnaires to several respondents from the Supervisory Consultant and Implementing Contractor with a total of 6 respondents.
Based on the results of PDM analysis with the help of Microsoft Project 2021, a comparison of the total duration of work based on plan, realisation and estimation scheduling was obtained, namely in the plan scheduling for 272 days, realisation scheduling for 249 days, and estimation scheduling for 267 days.
Based on the three schedules, the work with the most critical status is obtained in Preparatory Work, Concrete Structures, Doors and Windows, Electrical and Electrical, and Procurement of Equipment Etc. And from the results of the questionnaire recapitulation, it is concluded that the influencing factors in the construction process of this project are unstable weather, material supply mobilisation process, and lack of manpower.
Keywords : Critical and Non-Critical Path, Microsoft Project 2021, Rescheduling, Precedence Diagram Method (PDM)
Full Text:
PDFReferences
Atin Nori Cahyana, S. (2017). Utilisation of Precedence Diagram Method (PDM) in Project Scheduling at PT X. Proceedings of SAINTIKS FTIK UNIKOM, 2.
Cahyaningsih, Y. Rescheduling Analysis Using the PDM Method (Precedence Diagram Method) and Mitigation (Case Study of BBPJN XI/PJN I Kalimantan Flats Construction Project).
Fitrianto, R. (2019). Construction Project Scheduling with PDM Scheduling Method (Precedence Diagram Method) And Time Calculation With PERT (Program Evaluation And Review Technique) (Case Study : Construction Project of Sultan Agung-UII Kindergarten Building Phase II, Nglanjaran, Sleman).
Indah Pratama, P. R. I. S. C. A. (2024). Rescheduling With Precedence Diagram Method (PDM) On the Construction Project of Learning Support Building of State University of Malang (Doctoral dissertation, ITN Malang).
Marina, M., & Kartadipura, R. H. (2021). Scheduling Study Using CPM and PDM Methods with Microsoft Project 2019 on the Darul Hijrah Putera Martapura Cottage Construction Project. Journal of Sustainable Technology, 10(02), 65-71.
Mulia, T. N., & Candra, R. (2023). Project Scheduling Analysis Using Critical Path Method (CPM) Case Study on the Construction of the Archway of the Protected Forest Park in Langsa City. Journal of Accounting Economics Research (JENSI), 7(1), 82-90.
Nurcahya, N. R., Yuliana, C., & Widiastuti, E. (2023). Rescheduling Using The PDM Method With Microsoft Project 2021 In The Urban Slum Quality Improvement Project For Air Santri, Banjar Regency. Cerucuk, 7(1), 1-12.
Oktavia, N. (2018). Scheduling Planning for Apartment Construction Project in Surabaya with Precedence Diagram Method (PDM) (Doctoral dissertation, Brawijaya University).
Safitri, D. A. Scheduling Analysis Using CPM and PDM Methods with Microsoft Project 2019 on the Salim Mataraman River Bridge Replacement Project.
Sari, D. A. Comparative Analysis of Project Scheduling Time with PDM and PERT Methods (Case Study : Kiram-Gunung Mawar Road Rehabilitation Project).
Sobirin, Z. A., & Cahyaka, H. W. (2014). Analysis of the Appropriateness of the Design of the New Sports Building of Surabaya State University to the Concept of Green Building. Journal of Civil Engineering, 3, 29-36.
Sodikin, A. I. (1999). Multipurpose Building in Ciamis Traditional Architecture of West Java Region as a Determining Factor of Appearance Design.
Sorongan, V. M., Dundu, A. K., & Tjakra, J. (2022). Analysis of Project Scheduling Using the PDM Method Using the Concept of Time Reserve on the Tondano-Kembes-Manado Section 2 Road Improvement Project. TEKNO, 20(81).
Suputra, I. G. N. O. (2011). Project Scheduling With Precedence Diagram Method (PDM) dan Ranked Position Weight Method (RPWM). Scientific Journal of Civil Engineering, Vol. 15(1).
Syaputra, I. (2019). Analysis of Project Work Implementation Scheduling with CPM and PDM Methods on Road Improvement Sei Pakning (KM 130) - Teluk Masjid - Simpang Pusako Siak Regency (Doctoral dissertation, Riau Islamic University).
Winata, D. H. (2021). Time Scheduling Planning With PDM Method (Precedence Diagram Method) on the Construction Project of the Regional Government Representative Office in Tapan. Abstract of Undergraduate Research, Faculty of Civil and Planning Engineering, Bung Hatta University, 1(1), 1-2.
DOI: https://doi.org/10.20527/crc.v9i1.14731
Refbacks
- There are currently no refbacks.
Copyright (c) 2025 Dhika Fitrianita Putri, Endah Widiastuti, Humaira Afrila, Gawit Hidayat

This work is licensed under a Creative Commons Attribution 4.0 International License.
Indexed By:
GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0