ANALYSIS OF LABOR COEFFICIENT IN COLUMN STRUCTURE WORK (CASE STUDY OF THE CONSTRUCTION PROJECT OF THE HIGH PROSECUTOR'S OFFICE OF SOUTH KALIMANTAN PROVINCE)
Abstract
Along with the development of the times, the construction of buildings is also increasing rapidly. In a project, planning the budget of a project using the method of analyzing the price of the unit of work is very necessary as a reference. In the analysis of the unit price of work, there is also a labor coefficient planning which aims to measure the efficient use of labor in a construction project and can optimize the use of human resources in a construction project.
The data collection method used is using the work sampling method. Work Sampling is a method that can be used to measure productivity. The productivity value of the workforce can be seen from the results of the standard time calculation. Standard time is the time that can be completed by the workforce in completing work under standard conditions.
The results of the research conducted on the South Kalimantan Provincial High Prosecutor's Office Construction project obtained the value of the labor coefficient in the column structure work in the field which was compared with the labor coefficient in the planning column structure work. Between the two analyses there is a clear difference due to the difference in work methods carried out in the field. This results in the value of the labor coefficient in the field tending to be smaller than the value of the planned labor coefficient.
Keywords: Coefficient, Labor, Column
References
Efrizal, F. (2019). Analysis of Labor Productivity in Column Work
on a housing project in Pekanbaru (Doctoral dissertation, Islamic University of Riau).
Faustine, C., & Waty, M. (2022). Ranking of Influencing Factors
Labor Productivity in Construction Projects. JMTS: Jurnal Mitra
Civil Engineering, 681-692.
Gunawan, A., & Setyawan, A. (2022). Productivity Analysis of Work Results
Construction Between Normal Work and Overtime Work. Surakarta Civil Engineering Review (SCER), 2(1), 49-61.
Hernandi, Y., & Tamtana, J. S. (2020). Influencing Factors
Worker productivity in the implementation of multi-storey building construction. JMTS: Journal of Civil Engineering Partners, 299-312.
Lalujan, A. N., & Sutandi, A. (2022). Labor Productivity Analysis on
Repeating work in Manado City with the work sampling method. JMTS: Journal of Civil Engineering Partners, 661-670.
Leonardy, E., & Sekarsari, J. (2020). Analysis of Iron Work Coefficients in
Construction of a multi-storey building. JMTS: Journal of Civil Engineering Partners, 1327-1334.
Mahapatni, I. A. P. S. (2019). Project Planning and Control Methods
Construction.
Natalia, M., Adibroto, F., & Lubis, R. (2020). Power Productivity Comparison
Work with the Time Study Method on AHSP SNI 2016. Cycle: Journal of Civil Engineering, 6(2), 155-166.
Regulation of the Minister of Public Works and Public Housing Number 8 of 2023
about Guidelines for the Preparation of Construction Work Cost Estimates in the Field of Public Works and Public Housing.
Rubiana, F. (2019). Comparison of Labor Unit Price Coefficient Analysis
In the Field and Analysis of SNI 2016 on the Drainage Work Project (Case Study: Intan Sari Raya Road Improvement Work Project Banjarbaru City).
Law of the Republic of Indonesia No. 13 of 2003 concerning Manpower.
DOI: https://doi.org/10.20527/crc.v9i2.14838
Refbacks
- There are currently no refbacks.
Copyright (c) 2025 Nadiya Maharani, Abdul Karim

This work is licensed under a Creative Commons Attribution 4.0 International License.
Indexed By:
GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0