SCHEDULING ANALYSIS USING THE PRECEDENCE DIAGRAM METHOD (PDM) METHOD IN THE PHASE II BRIDGE CONSTRUCTION PROJECT IN PEJAMBUAN VILLAGE, SUNGAI TABUK DISTRICT, BANJAR REGENCY, SOUTH KALIMANTAN
Abstract
In its implementation, starting from the planning stage, the implementation of scheduling, to the supervision and implementation of good controls, construction projects need to be well managed in their work. In the process of Building the Phase II Bridge Project in Pejambuan Village, Sungai Tabuk District, there was a slight delay in the eighth week due to equipment damage and delays in the material supply mobilization process. This project only has a time schedule in the form of an S Curve which is not helpful in controlling work in the field.
This study aims to analyze scheduling using the Precedence Diagram Method (PDM) method assisted by the Microsoft Project 2021 application and identify critical and non-critical paths of work so that the implementation of the project can be carried out with an effective duration.
Based on the results of the analysis of this study, the total duration of work is 138 working days with the total duration of work calculated using calendar days for 174 days, and the total duration of project realization is 180 calendar days. CV planning calculation. Al Fatih Karya is scheduled to be completed by September 30, 2024, while scheduling with the PDM method is completed by September 24, 2024. The critical trajectory in the results of this analysis is found in 13 activities starting from ordinary excavation work and ending with the installation of bridge nameplates.
Keywords : Bridge, Microsoft Project 2021, Scheduling, Delay, PDM
Full Text:
PDFReferences
Aulia, S. S. (2021). Analysis Of Building Project Scheduling Using The CPM-PERT Method. Islamic University of Indonesia, 117.
Gazalba, Z., Gede Putu Warka, I., Wirahman, L. W. Evaluation of the Fairness of Contractor Schedules Using Work Breakdown Structure (WBS) and Microsoft Project (Study on the Construction Project of SDN 5 Sokong, Tanjung, North Lombok). Journal of Ganec Swara, 16(1). http://journal.unmasmataram.ac.id/index.php/GARA
Isnandar, K., Rambe, M. R., & Puspita, N. R. (2023). Analysis of the Scheduling of the Padangmatinggi Health Center Building in Padangsidimpuan City Using the CPM (Critical Path Method) Method. Statics Journal of Civil Engineering, 6(1), 19–30. https://jurnal.ugn.ac.id/index.php/statika
Oktavia, N. (2018). Planning for Scheduling Apartment Construction Projects in Surabaya with the Precedence Diagram Method (PDM). http://repository.ub.ac.id/id/eprint/12527/
Situmorang, P. D. (2017). Project Scheduling Analysis with Time Schedule Curve S, Precedence Diagram Method (PDM) and Ranked Positional Weight Method (RPWM). Journal of Civil Engineering, University of North Sumatra, 3(7), 93-112.
Syaputra, I. (2019). Analysis of Scheduling Project Work Implementation with CPM and PDM Methods on the Improvement of Jalan Sei Pakning (Km 130) – Teluk Masjid – Simpang Pusako, Siak Regency. KM 130.
Tasha Nadia Mulia, Surbakti, S., & Riny Candra. (2023). Project Scheduling Analysis Using the Critical Path Method (CPM) Case Study on the Construction of Langsa City Protected Forest Park Gate. Journal of Accounting Economics Research (JENSI), 7(1), 82–90. https://doi.org/10.33059/jensi.v7i1.7731
Virgina, H. (2019). Comparative Analysis of Project Scheduling Time with CPM (Critical Path Method) and PERT (Project Evaluation and Review Technique) Methods (Case Study: Marigold Ciputra Botanical Pangkal Pinang Housing). http://unugha.ac.id
Winata, D. H., Khaidir, I., & Zulfrimar. (2021). Time Scheduling Planning with the PDM Method (Precedence Diagram Method) on the Construction Project of the Regional Government Representative Office in Tapan.
DOI: https://doi.org/10.20527/crc.v9i2.14841
Refbacks
- There are currently no refbacks.
Copyright (c) 2025 Alfisyah Oktarina Pinanggi, Abdul Karim, Endah Widiastuti

This work is licensed under a Creative Commons Attribution 4.0 International License.
Indexed By:
GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0