EVALUATION STUDY OF THE CONSTRUCTION SCHEDULE OF THE GUNUNG KUPANG RESERVOIR WITH ADDITIONAL WORKING HOURS USING THE CRASHING METHOD

Muhammad Aulia Rahman, Eliatun Eliatun

Abstract


In development, there are often obstacles and success factors. Delays in the work of a project are considered very detrimental so that scheduling is accelerated by one method, namely by crashing.In the Gunung Kupang Reservoir Development Project, Cempaka District, Cempaka District, experienced a delay in realization due to the implementation of inappropriate work methods. An alternative is carried out in the form of acceleration of the remaining work by applying the crash program method with additional working hours.

The crash program  is carried out on activities that are on a critical trajectory with the help of a scheduling application. Then crashing is carried   out on the rest of the work with the alternative of adding 3 (three) working hours and 4 (four) working hours. After the crashing results are obtained , a comparison of time and cost efficiency is carried out between the work by paying fines, and adding working hours.

From the results of the study, it was found that work by paying fines is a more efficient method of implementation than accelerating. Where the implementation cost by paying a fine has a total cost of Rp. 3,678,274,868.15 while accelerating the project for 3 (three) hours with a total cost of Rp. 3,721,415,450.19, and accelerating the project for 4 (four) hours with a total cost of Rp. 3,700,800,405.34. So that an efficient cost budget is to do the work by paying fines rather than accelerating.

Keywords: Construction delays, Project Acceleration, Scheduling apps, crash program, Addition of working hours.


Full Text:

PDF

References


Anggraeni, Elisabeth Riska. Hartanto, Widi. Sugiyarto. 2017. Analisis Percepatan Proyek Menggunakan Metode Crashing Dengan Penambahan Tenaga Kerja Dan Shift Kerja (Studi Kasus : Proyek Pembangunan Hotel Grand Keisha, Yogyakarta). (Tidak diterbitkan), Universitas Sebelas Maret.

Ervianto. 2005. Manajemen Proyek Konstruksi, Edisi Revisi. Yogyakarta: Andi.

Hanna, 2008. Impact Of Shift Work On Labor Productivity For Labor Intensive Contractor. Journal Of Construction Engineering And ManagementPeraturan Pemerintah No. 43. (1993). Tentang Prasarana dan Lalu Lintas Jalan. Jakarta: Pemerintah Republik Indonesia.

Husen. 2009. Manajemen Proyek: Perencanaan, Penjadwalan, dan Pengendalian Proyek. Yogyakarta: Andi.

Keputusan Menteri Tenaga Kerja No. KEP-102/MEN/VI/2004 Tentang Waktu Kerja Lembur Dan Upah Kerja Lembur (online). (Tidak diterbitkan), https://www.scribd.com/doc/131149015/KEPMEN-102-MEN-VI-2004, accessed on August 03, 2024

Peraturan Presiden Nomor 70 Tahun 2012 Tentang Pengadaan Barang dan Jasa (online). (Tidak diterbitkan), https://jdih.lkpp.go.id/regulation/peraturan-presiden/peraturan-presiden-nomor-70-tahun-2012 accessed on May 12, 2024

Peraturan Presiden (PERPRES) Nomor 12 Tahun 2018 Tentang Pengadaaan Barang/Jasa Pemerintah (online). (Tidak diterbitkan), https://jdih.lkpp.go.id/regulation/peraturan-presiden/peraturan-presiden-nomor-12-tahun-2021, accessed on May 14, 2024

Perhitungan Denda Keterlambatan Pekerjaan menurut PERPRES Nomor 16 Tahun 2018 (online). (Tidak diterbitkan), https://fakpi.org/2018/07/02/denda-keterlambatan-pekerjaan-berdasarkan-perpres-nomor-16-tahun-2018/ accessed May 12, 2024

Saputra Roni Gustian. 2023. Evaluasi Jadwal Pelaksanaan Pekerjaan Pembangunan Jembatan Gantung Ds. Batuah Dengan Penambahan Jam Kerja Dan Alat Kerja Menggunakan Metode Crashing. Tugas Akhir. Fakultas Teknik. Universitas Lambung Mangkurat: Banjarbaru




DOI: https://doi.org/10.20527/crc.v9i5.15308

Refbacks

  • There are currently no refbacks.


Copyright (c) 2025 Muhammad Aulia Rahman, Eliatun Eliatun



Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License. 

joomla
statistics View My Stats

Indexed By:

 

GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0