ANALYSIS OF OVERTIME WORK PRODUCTIVITY AND WAGE SUITABILITY IN THE WORKFORCE OF THE BANJARMASIN-MARTAPURA ROAD RECONSTRUCTION PROJECT SECTION II
Abstract
In an effort to meet the deadline for the Banjarmasin – Martapura Road Reconstruction Project Section II, the implementing party often accelerates the schedule by implementing an overtime work system. To determine the labor productivity of the Banjarmasin – Martapura Road Reconstruction Project Section II, this study uses the partial productivity method. This method compares the time used per day as the input value with the amount of work produced each day as the output value.
The results of the calculation obtained from the productivity analysis using a partial approach are obtained that the average productivity of normal working hours in paving work is 15,923 m3/hour and in road shoulder casting work is 1,877 m3/hour. The average productivity of overtime working hours for paving work was 16,285 m3/hour and for casting work was 2,190 m3/hour. From the results obtained, it is known that the productivity value of overtime working hours is greater than the productivity of normal working hours, this is due to obstacles that occur, namely the asphalt and concrete production process from AMP (Asphalt Mixing Plant) which is late because the engine that often breaks down is also because this road project is in the middle of a dense community so that the material process to the location often experiences delays. By implementing overtime working hours, the labor wage budget increased by 86.717%. However, the amount of overtime wages implemented by the Banjarmasin – Martapura Road Reconstruction Project Section II is not in accordance with the amount of wages according to the provisions of Government Regulation No. 35 of 2021.
Keywords: Partial productivity, overtime work, overtime wages, labor
Full Text:
PDFReferences
Budijanto, O. W. (2017). Living wages for workers/laborers from the perspective of Law and Human Rights. De Jure Journal of Legal Research, 17(3), 395-412.
Eliatun, E., & Tjitradi, D. (2021). Analysis of Acceleration Using the Crashing Method in the Construction Project of Building X in Banjarmasin. Kacapuri Journal: Journal of Civil Engineering Science, 5(1), 72-82.
Ervianto, W, I, 2008, Measurement of Productivity of Construction Workers in Construction Projects (Case Study of Multi-storey Building Project in Surakarta). Journal of Civil Engineering 9(1).
Ervianto, I. W. 2005. Construction Project Management Theory-Applications. Yogyakarta: Andi.
Eto, A., Tuloli, M. Y., & Rachman, H. A. Project Implementation Time Planning Using the Pert Method in Periodic Maintenance Work of Large Rice Fields Road. J. Perad. Science, Engineering and Technology, 5(2), 221-229.
Fahirah, F. (2005). Identify the causes of overrun of building construction project costs. SMARTek, 3(3).
Firmansyah, M. R., Nugroho, M. W., Yulianto, T., & Majid, A. (2021). Time Schedule Analysis of the Tambakrejo-Jombang Health Center Building Rehabilitation Project. Reaktip: Journal of Civil Engineering and Applications, 1(1), 47-56.
Indonesia. Law Number 11 of 2020 concerning Job Creation. Statute Book of the Republic of Indonesia Year 2020 Number 11, Supplement to the Statute Book of the Republic of Indonesia Number 4279. State Secretariat. Jakarta.
Jawat, W. (2015). Method of Implementing Foundation Work (Study: Fave Hotel Kartika Plaza Project). PADURAKSA: Journal of Civil Engineering, Warmadewa University, 4(2), 22-34.
Laksono, T. D. (2007). Productivity on construction projects. Theodolita: Scientific Communication Media in the Field of Engineering, 8(2).
Nugroho, P. S. (2012). Increasing construction productivity through the selection of construction methods. Engineering Dynamics, 8(1), 25-30.
Guidelines for Improving the Professionalism of Construction Human Resources, 2007.
Government Regulation Number 35 of 2021 concerning Certain Time Work Agreements, Outsourcing, Working Time and Rest Time, and Termination of Employment.
Simanjuntak P.J., 2005, Performance Management and Evaluation, Publishing Institute, Faculty of Economics, University of Indonesia, Jakarta.
Sinungan, Muchdarsyah. 2003. What and How Productivity. Jakarta: Bumi Aksara.
Subagyo, U., Raharjo, N. D., Khamim, M., & Raharjo, B. A. (2021). Technical Assistance for the Implementation of Painting of the Rw Xi Hall, Jalan Silikat, Purwantoro Village, Blimbing District, Malang Municipality. Journal of Community Service, 8(1), 13-17.
Sugiyono, 2001. Statistics for Research. Bandung: Alfabeta.
Tabita, N.C., 2024, Analysis of Overtime Work Productivity in Construction Workers of the Syamsuddin Noor International Airport Access Road Construction Project. Final Project: Lambung Mangkurat University
Wignjosoebroto, Sritomo, 2006, Ergonomics, Motion and Time Studies. First Edition, Fourth Edition, Surabaya: Guna Widya
Wilson, Wijaya. 2018. The Effect of Overtime Work on Construction Work Productivity in Sukaramai Flats. Final Project: University of North Sumatra
Yuliana, C. (2013). Analysis of the factors causing delays in the implementation of bridge construction projects. INFO-TEKNIK, 14(2), 114-125.
DOI: https://doi.org/10.20527/crc.v9i3.16427
Refbacks
- There are currently no refbacks.
Copyright (c) 2025 Ahmad Badarudin, Candra Yuliana, Humaira Afrila

This work is licensed under a Creative Commons Attribution 4.0 International License.
Indexed By:
GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0