ANALYSIS OF OVERTIME WORK PRODUCTIVITY IN CONSTRUCTION LABOR ON THE SYAMSUDDIN NOOR INTERNATIONAL AIRPORT ACCESS ROAD CONSTRUCTION PROJECT
Abstract
In order to reach the target plan on the Syamsuddin Noor International Airport Road Construction project, the contractor applied overtime working hours for the labor. The application of overtime working hours requires issues on budget. This overtime productivity measurement is useful to find out the effectiveness of the overtime working hour.
One of the methods for measuring labor productivity is using the partial productivity approach, which can be measured by knowing the input and output values of the equation of partial production. For the calculation of labor productiveness of the Syamsuddin Noor Internasional Airport Access Road Construction project, the input value is the amount of time used per day, whereas the output value is the amount volume of work produced per day.
The result from this analysis with a partial productivity approach found that the average productivity of normal working hours was 1661,87 m/hour for galam pile work and 17,83 m3/hour for embankment work. Furthermore, the average productivity of overtime hours was 2715,46 m/hour for galam pile work and 41,31 m3/hour for embankment work. The results show that overtime working hour productivity is higher than normal working hour productivity, which can be caused by some reasons. The main obstacle is rainy weather that requires work to be temporarily stopped and can only be continued when the rain stops or even sometimes have to wait for the site to be dry enough. The application of overtime working hours increases the wage budget by 30,38%. However, the overtime labor cost applied in the Syamsuddin Noor International Airport Access Road Construction project is not in line with the overtime labor cost based on provisions of PP Number 35 Year 2021.
Keywords: Partial productivity, labor, overtime working hours, overtime labor cost.Full Text:
PDFReferences
Andre, Tedjowidjojo. 2013. The Effect of Leadership Style and Work Motivation on Worker Performance on Construction Projects in Yogyakarta. Thesis: Atma Jaya University Yogyakarta.
Cornelia, B, 2003. Analysis of Labor Productivity in Relation to Time and Implementation of Construction Projects. Thesis: Udayana University.
Ervianto, I. W. 2004. Theory-Application of Construction Project Management. Yogyakarta: Andi.
Eliatun & Tjitradi, D. 2022. Acceleration Analysis with Crashing Method on Building X Construction Project in Banjarmasin. Journal of Civil Engineering Science. 5 (1) : 72-82
Febrian, M. A. 2023. Productivity of Overtime Working Hours in Construction Labor of Sp. Handil Bakti-Marabahan-Kandangan Road Preservation Project. Thesis: Lambung Mangkurat University
Husen, Adrianto. 2011. Project Management 1st Revised Edition. Yogyakarta. Publisher: Andi Offset.
Indonesia. Law Number 11 of 2020 concerning Job Creation. Indonesian State Gazette of 2020 Number 11, Supplement to Indonesian Gazette number 4279. State Secretariat. Jakarta.
Guidelines for Improving the Professionalism of Construction Human Resources, 2007
Government Regulation No. 35 of 2021 Concerning Fixed-Term Employment Agreements, Outsourcing, Working Time and Rest Time, and Termination of Employment Relationships
Rani, I. 2014. Comparative Analysis of the Acceleration of Work Implementation in View of the Addition of Labor and the Addition of Working Hours in the ITERA Phase I Building Construction Project. Thesis: University of Lampung.
Santosa, B. 2013. Project Management: Concept & Implementation. Yogyakarta: Graha Ilmu
Santoso, B. G., & Chandra, J. 2006. Relationship between Over Time and Productivity of Masonry Work (Case Study on Projects X, Y, and Z). http://digilib.petra.ac.id.
Sarjono, Haryadi. 2001. Productivity Measurement Model Based on Output Per Input Ratio Approach. Journal The Winners. 2 (2) : 130-136.
Simanjuntak P.J., 2005. Performance Management and Evaluation. Publishing House of the Faculty of Economics, University of Indonesia, Jakarta.
Sinungan, Muchdarsyah. 2003. Productivity What and How. Jakarta: Bumi Aksara.
Soeharto, Imam. 1999. Project Management: From Conceptual to Operational. Jakarta: Erlangga.
Highways General Specifications for Road and Bridge Construction Works
Sugiyono, 2001. Statistics for Research. Bandung: Alfabeta.
Widyatmoko, Yurry. 2008. Analysis of Time Acceleration Using Crashing Method on Piling Activity in Tanjung Priok Pier 115 Project with PERTMaster Program Application. Thesis: University of Indonesia.
Wilson, Wijaya. 2018. The Effect of Overtime on Construction Work Productivity at Sukaramai Flats. Thesis: University of North Sumatra.
Yuliana, Candra. 2013. Analysis of Factors Causing Delays in the Implementation of Bridge Construction Projects. Engineering Info. 14 (2) : 114-125.
DOI: https://doi.org/10.20527/crc.v10i2.18911
Refbacks
- There are currently no refbacks.
Copyright (c) 2026 Neysa Claretha Tabita, Retna Hapsari Kartadipura

This work is licensed under a Creative Commons Attribution 4.0 International License.
Indexed By:
GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0