SCHEDULING ANALYSIS USING THE PDM METHOD IN THE SYAMSUDIN NOOR AIRPORT ACCESS ROAD CONSTRUCTION PROJECT WITH THE HELP OF MICROSOFT PROJECT

Nurisma Witami, Husnul Khatimi

Abstract


Syamsudin Noor Airport Access Road Development Project, Landasan Ulin Sub-district, Banjarbaru City, South Kalimantan is a provincial road project carried out by the PUPR Office of South Kalimantan Province together with the Banjarmasin National Road Implementation Center. This project is carried out within 330 working days based on the schedule given in the form of Barchart. The implementation of this project should be completed in the shortest possible time, so that scheduling analysis is carried out using other methods, one of which is the Precedence Diagram Method (PDM). Through the results of the analysis in this study, it was found that the total duration of scheduling the Syamsudin Noor Airport Access Road Construction Project using the PDM method with the help of Microsoft Project was 221 working days and 270 calendar days, the total initial duration of the project was for 330 working days. The work started on September 25, 2023 and ended on 21 June, 2024.

 

Keywords: Project, Scheduling, PDM, Project


Full Text:

PDF

References


Alviani E. (2023). Scheduling Management Using Microsoft Project and Risk Analysis on the University of Lampung RSPTN Construction Project. Faculty of Engineering, University of Lampung. Bandar Lampung.

Cipta I. (2020). Analysis of the Application of Time Management in Road Projects in Lamongan Regency. Civil Engineering Study Program, Faculty of Engineering, Lamongan Islamic University, Indonesia. ISSN 2549-6379 (Print) ISSN 2549-6387 (Online).

Chyntia M.M., et al. (2024). Application of Critical Path Method (CPM) in Analyzing Time Management in Advertising Planning for Digital Marketing Gims. Scientific Journal of Mathematics, Mathematics and Statistics Education. Vol. 5, No. 2. p-ISSN 2721-8929 e-ISSN 2721-8937.

Fazis M., & Tugiah. (2022). Project Planning and Project Scheduling. Journal of Social and Technology (SOSTECH) Volume 2 , Number 12 , December 2022 p-ISSN 2774-5147 ; e-ISSN 2774-5155.

Nugraha A.S., & Sumarman. (2017). Analysis of Construction Management of the Construction of Samsat Office of the Provincial Service Branch in the Majalengka Area, Majalengka Regency. ISSN Construction Journal: 2085 – 8744. UNSWAGATI CIREBON.

Nurjanah, et al. (2024). Construction Project Scheduling Training with Microsoft Project to Create Civil Engineering Students. Journal of Community Service: Empowerment, Innovation and Change ISSN (Online): 21008-3407;Vol. 4, No. 4.

Marques, J. F., & Bernardino, J. (2019). Evaluation of Asana, Odoo, and ProjectLibre Project Management Tools using the OSSpal Methodology. In KEOD(pp. 397-403).

Maslina, et al. (2023). Analysis of the scheduling of the Rehabilitation Project of the Preservation Road of Jalan Kerang – Kuaro, East Kalimantan using the PDM and PERT methods. TRANSUKMA Journal Volume 05 Number 02.

Sajad M., Sadiq, M., Naveed, K., & Iqbal, M. S. (2016). Software Project Management: Tools assessment, Comparison and suggestions for future development. International Journal of Computer Science and Network Security (IJCSNS), 16(1), 31.

Satrio G., & Latief, Y. (2018). Development of risk-based standardized WBS (Work Breakdown Structure) for safety planning of cable-stayed bridge project. In Proceedings of the international conference on industrial engineering and operations management (Vol. 12, No. 2, pp. 110-117).

Siagian M.D., et al. (2017). Optimizing Scheduling with Network Analysis on Book Collection Verification Activities in School Libraries. InfoTekJar : National Journal of Informatics and Network Technology ISSN (Print) 2540-7597 | ISSN (Online) 2540-7600.

Soplanit N., et al. (2021). Analysis of the Application of the Line Of Balance Method in the Construction of Flats of the Tanimbar Islands Regency Government. SYMMETRIC JOURNAL VOL 11, NO. 2.

Suherman, & Ilma A. (2016). Project Scheduling Analysis Using PDM and Pert and Crash Project (Case Study: Construction of the Main Power House Building of PT. Adhi Karya). Journal of Research Results and Scientific Works in the Field of Industrial Engineering. Vol. 2, No. 1.

Suwinardi, (2015). Scheduling and development of project plans. ORBITH VOL. 11 NO. 3 NOVEMBER 2015 : 223 – 229.

Teguh R., M.T., & Sudiadi, M.M.A.E., (2015). Project Management. Information Systems Study Program, College of Informatics Management, Gi Mdp, Palembang.




DOI: https://doi.org/10.20527/crc.v10i3.18916

Refbacks

  • There are currently no refbacks.


Copyright (c) 2026 Nurisma Witami, Husnul Khatimi



Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License. 

joomla
statistics View My Stats

Indexed By:

 

GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0