ANALYSIS OF HEAVY EQUIPMENT PRODUCTIVITY IN THE BINDEREANG-SUNGAI IMPAT ROAD RECONSTRUCTION PROJECT

Nor Nida Yuliana, Husnul Khatimi

Abstract


The reconstruction of Jalan Binderang-Sungai Impat is carried out to improve the of the road. The use of heavy equipment is very important to help the work and speed up the work process. The purpose of this study is to analyze the productivity of heavy equipment and the total time in the work of the aggregate foundation layer of class A, as well as to compare the productivity of heavy equipment calculated based on theory with field data and productivity based on field implementation

In the analysis, a heavy equipment calculation method based on the Minister of PUPR Regulation No. 08 of 2023 was used to calculate theoretical productivity. In addition, observations and direct interviews were carried out in the field to obtain data on equipment working hours, types of heavy equipment, and the capacity of the tools used to calculate field productivity. For general project data, tool specifications and work volumes are obtained from the contractor or consultant.

Through the results of the analysis in this study, the theoretical productivity results of heavy equipment for wheel loaders 111.27 m3/hour, dump trucks 5,303 m3/hour, motor graders 132.69 m3/hour, vibratory rollers 78.54 m3/hour and water tank trucks 71.14 m3/hour were obtained. The total theoretical time for the work of the aggregate foundation layer of class A is 3 days, while based on the implementation in the field the time required is 10 days. Based on the theorectical analysis the number of dump truck 21units while in the field the number of dump truck used is 17 units. For onther types of heavy equipment, the fleet size is the same with 1 units both in the theoretical analysis amd in the field reality.

 

Keywords: Heavy equipment, productivity, duration, number of equipment


Full Text:

PDF

References


Hermawan, A. (2023). "Analysis of Ground Surface Unevenness in Infrastructure Projects." Indonesian Journal of Civil Engineering, 15(2), 101-110.

Liutari, A., Tui, R. N. S., Amalia, R., & Anas, A. V. (2022). Optimization of D8R Dozer production at Hasan Disposal Pt Vale Indonesia Tbk using the Linear Programming method. Journal of Mining, 6(3), 124–131.

Nurhendi, R. N., & Bastam, M. N. (2023). Factors Affecting Construction Labor Productivity: A Literature Review. Journal of Civil Engineering, 13(1), 53–65.

Regulation of the Minister of Public Works and Public Housing Number 8 of 2023 concerning Guidelines for the Preparation of Construction Work Cost Estimates in the Field of Public Works and Public Housing.

Prima, G. R., & Hafudiansyah, E. (2022). PRODUCTIVITY OF HEAVY EQUIPMENT IN TOLL ROAD PROJECT WORK (Case Study: Pematang Panggang – Kayu Agung Toll Road Section 2, Ogan Komering Ilir, South Sumatra). Acceleration : Scientific Journal of Civil Engineering, 3(2), 74–81.

Purwandanu, A., Sari, D. R., & Hidayat, R. (2020). "Analysis of Dump Truck Cycle Time on Construction Projects." Journal of Civil Engineering, 8(1), 45-56.




DOI: https://doi.org/10.20527/crc.v10i3.18917

Refbacks

  • There are currently no refbacks.


Copyright (c) 2026 Nor Nida Yuliana, Husnul Khatimi



Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License. 

joomla
statistics View My Stats

Indexed By:

 

GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0