COMPARISON OF SCHEDULING USING CPM AND PDM METHODS IN THE RECONSTRUCTION PROJECT OF JALAN BUMI MAKMUR – PULAU SARI, BUMI MAKMUR DISTRICT, TANAH LAUT REGENCY, SOUTH KALIMANTAN
Abstract
Construction projects in their implementation require the success of management because they are very important for the project. For a smooth work process, effective management is needed to manage project scheduling from start to finish. Therefore, in the Bumi Makmur – Pulau Sari Road Reconstruction project, scheduling will be made using diagrams with PDM, CPM, and modified CPM.
The Precedence Diagram Method (PDM) scheduling method in the construction industry is scheduling that can be done with several dependencies where there is an overlapping relationship. While the Crictical Path Method (CPM) method, which is the dependence of finish to start work, then in this study will be modified, namely a work item is divided into several segments of work activities.
The results obtained from the research conducted on the scheduling of this project for the PDM method of the project can be carried out in 136 days. Meanwhile, the CPM method of the project can be done in 225 days and for the CPM method of project modification it can be done in 145 days. The three methods have critical paths, in PDM all activities have a critical path and only have 1 critical path, while in the CPM method without modification there is 1 critical path, and in modified CPM there are 2 critical paths.
Kata kunci: Crictical Path Method (CPM), Precedence Diagram Method (PDM)
Full Text:
PDFReferences
Dannyanti, E. (2010). OPTIMIZATION OF PROJECT IMPLEMENTATION WITH PERT AND CPM METHODS. Thesis: Diponegoro University.
Hassan, H. (2016). FACTORS CAUSING DELAYS IN CONSTRUCTION PROJECTS AND ALTERNATIVE SOLUTIONS (CASE STUDY: IN MANADO TOWN SQUARE III). Static Civil Journal Vol.4 No.11, 657-658.
Husen. (2008). Project Management. Yogyakarta: Andi Offset.
Husen, A. (2009). Project Magazine. Yogyakarta: C.V ANDI OFFSET.
Idzurnida, I. (2013). DELAYS IN BUILDING CONSTRUCTION PROJECTS, CAUSATIVE FACTORS AND PREVENTIVE MEASURES. Momentum Journal.
Kerzner, H. (2006). Project Management: A Systems Approach To Planning, Scheduling, Controling , 9th edition, United State of America.
Lawrance, J. a. (2001). Applied Management Science: Modeling Spreadsheet Analysis, and Communication For Decision Making. United States of America: John Wiley and Son.
Malifa, Y. (2019). ANALYSIS OF CONSTRUCTION TIME AND COST OF CONSTRUCTION PROJECTS USING THE CRASHING METHOD (CASE STUDY: CONSTRUCTION OF IAIN MANADO FLATS). Static Civil Journal Vol.7 No.6 , 681-688.
Mangare, T. A. (2017). PLANNING THE COMPLETION TIME OF THE MODISLAND MANADO STORE PROJECT USING THE CPM METHOD. Static Civil Journal , 549-557.
Megawati, L. A. (2020). ANALYSIS OF DELAY FACTORS IN BUILDING CONSTRUCTION PROJECTS. Journal of Engineering.
Nurjaman, H. D. (2014). Project Management Edition 1. Bandung: Pustaka Setia.
Rabiah. (2016). EVALUATION OF SCHEDULING USING THE PRECEDENCE DIAGRAM METHOD AND ACCELERATION USING THE CRASH PROGRAM (CASE STUDY OF THE REGIONAL FINANCE AGENCY BUILDING PHASE 1). Final Project.
Safitri, E. (2019). Project Scheduling Optimization using CPM and PDM (Case Study: Construction of KUA Marriage and Manasik Hall Building, Indragiri Hilir Regency District). Journal of Mathematical Sciences and Statistics, Vol.5 No.2.
Simatupang, J. S. (2014). THE EFFECT OF DURATION ACCELERATION ON TIME IN CONSTRUCTION PROJECTS (CASE STUDY: EBEN HAEZER MANADO SCHOOL DEVELOPMENT). Static Civil Journal Vol.3 No.5, 281-280.
Sudipta, I. G. (2013). PROJECT MANAGEMENT STUDY OF RESOURCES IN THE IMPLEMENTATION OF CONSTRUCTION PROJECTS. Scientific Journal of Civil Engineering.
DOI: https://doi.org/10.20527/crc.v10i3.18919
Refbacks
- There are currently no refbacks.
Copyright (c) 2026 Rihadatul Isi Ramda, Candra Yuliana

This work is licensed under a Creative Commons Attribution 4.0 International License.
Indexed By:
GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0