TIME AND COST ANALYSIS OF PILE FOUNDATION WORK USING HYDRAULIC STATIC PILE DRIVER (Case Study: Construction Project of the Official Residence of the Governor of South Kalimantan)
Abstract
This study analyzes the productivity, time, and cost of foundation piling work using the Hydraulic Static Pile Driver (HSPD) on the Construction Project of the Official Residence of the Governor of South Kalimantan. Piling was carried out at 132 points with a total pile length of 1,584 meters. The results of the study show that the actual productivity reached 60.54 m/hour. The actual implementation time required only 4 working days or 28 hours, which is faster than the initial plan of 7 working days or 49 hours. This study did not include an analysis of the move-to-point time between pile locations. In terms of cost, the actual total cost amounted to IDR 187,246,000.00, which is lower than the estimated budget of IDR 201,608,500.00. These findings indicate that the actual implementation was more efficient in terms of both time and cost, and demonstrate the optimal performance of the HSPD in the field.
Keywords: Equipment Productivity, Construction Cost, Project DurationFull Text:
PDFReferences
Adianto, Y. L. D., Wimala, M., & Harun, A. M. (2022). Faktor faktor pengaruh besaran estimasi biaya tidak langsung pada penawaran pekerjaan jalan oleh kontraktor X [Factors influencing the magnitude of indirect cost estimates in road work bids by Contractor X]. Jurnal Rekayasa Sipil (JRS Unand), 18(1), 52.
Astuti, H. (2021). Analisis produktivitas alat tiang pancang terhadap biaya dan waktu pemancangan berdasarkan data perencanaan dan secara aktual [Analysis of pile driver productivity versus cost and time: planned vs. actual data] (Undergraduate thesis). Universitas Lambung Mangkurat.
Azhar, A. (2021). Analisis kerja alat pancang Hydraulic Static Pile Driver pada pekerjaan pondasi tiang pancang dari segi waktu dan biaya [Analysis of Hydraulic Static Pile Driver performance in pile foundation work in terms of time and cost] (Undergraduate thesis). Universitas Lambung Mangkurat.
Barnes, R. M. (1980). Motions and time study: Design and measurement of work (7th ed.). Prentice Hall International.
Bowles, J. E. (1991). Analisis dan desain pondasi (Vol. 2) [Foundation analysis and design]. Erlangga.
Dewi, E. P. (2020). Studi perbandingan efisiensi kerja alat pancang Diesel Hammer dan Drop Hammer pada pekerjaan pondasi tiang pancang dari segi waktu dan biaya [Comparative study of Diesel Hammer vs. Drop Hammer efficiency in pile foundation work: time and cost] (Undergraduate thesis). Universitas Lambung Mangkurat.
Dwiretnani, A., & Dauly, I. A. (2019). Kinerja alat Hydraulic Static Pile Driver (HSPD) pada proyek perluasan terminal Bandara Sultan Thaha Jambi [Performance of Hydraulic Static Pile Driver on the Sultan Thaha Jambi Airport terminal expansion project]. Jurnal Teknik Sipil ULM, 5(2), 45–53.
El Sawalhi, N. I., & El Riyati, A. (2015). An overhead costs assessment for construction projects at Gaza Strip. American Journal of Civil Engineering, 3(4), 95.
Ervianto, W. I. (2005). Manajemen proyek konstruksi [Construction project management] (Revised ed.). Andi Offset.
Hakim, A. R., & Akbar, A. (2018). Analisis produktivitas Hydraulic Static Pile Driver pada pembangunan Apartemen Victoria Square Tower B Tangerang Banten [Productivity analysis of HSPD in the construction of Victoria Square Tower B, Tangerang]. Jurnal Teoritis dan Terapan Bidang Rekayasa Sipil, 25(2), 103–112.
Hermawan, A. (2010). Analisis faktor pengelolaan kinerja produktivitas alat berat pada pekerjaan penggalian basement untuk bangunan gedung di DKI Jakarta [Analysis of heavy equipment productivity management factors in basement excavation for high rise buildings in Jakarta] (Master’s thesis). Universitas Indonesia.
Irfanto, R., Manulye, I. H., & Lidyawati, R. (2023). Analisa persentase komponen pembentuk RAB rumah relokasi Desa Ketapang [Analysis of cost estimate components for Ketapang Village relocation housing]. Indonesian Journal of Construction Engineering and Sustainable Development (CESD), 6(2), 12–21.
Jaya, N. M., & Ariany, F. (2015). An identification of construction project overheads for sustainable cost management and controlling practices. Applied Mechanics and Materials, 776, 121–126.
Joseph, E. B. (1991). Analisis dan desain pondasi (Vol. 2) [Foundation analysis and design]. Erlangga.
Rostiyanti, S. F. (2008). Alat berat untuk proyek konstruksi [Heavy equipment for construction projects]. Rineka Cipta.
DOI: https://doi.org/10.20527/crc.v10i5.18929
Refbacks
- There are currently no refbacks.
Copyright (c) 2026 Dhanu Wicaksono, Eliatun Eliatun

This work is licensed under a Creative Commons Attribution 4.0 International License.
Indexed By:
GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0