WORK ANALYSIS OF HYDRAULIC STATIC PILE DRIVER EQUIPMENT ON PILE FOUNDATION WORK IN TERMS OF TIME AND COST
Abstract
To make a building requires a strong foundation to withstand the load on it. the Physical Work Project, Renovation and Expansion of the District Court Building requires heavy equipment management in the form of piles, the piling method used is the Hydraulic Static Pile Driver. The pile management is needed to find out the estimated working time on the entire building so that the implementation goes according to or does not exceed the planned project time. Therefore, it is necessary to analyze the efficiency of the piling tool. The results of the descriptive analysis in this study obtained the production value of the Hydraulic Static Pile Driver tool. The highest production value was 0.23 meters/minute, and the lowest value was 0.21 meters/minute. The time required to complete the project erection work based on the planning is nine weeks, while the realization in the field to complete it in seven weeks. The planned implementation cost to complete the erection work for this project is Rp. 2,073,360,000. Meanwhile, the cost of field realization is Rp. 2,481,150,000. this means that the implementation costs in the field are greater than the planning costs of Rp. 407,790,000 this was due to the addition of 828.00 m3 of pile procurement volume and 828 m3 of piling and handling work, and 138 nos of pile connections.
Full Text:
PDFReferences
Dewi Eva Puspita. (2020). Comparative Study of Work Efficiency of Diesel Hammer And Drop Hammer On Pile Foundation Work In terms of time and cost. (Lambung Mangkurat University).
Erlan – Trijet., 2011). Productivity of Piling Tools Against Time Analysis in East Flood Canal Works (case study of East Flood Canal Development (BKT)
Hakim AR – Akbar A. (2018) Analysis of the Hydraulic Static Pile Driver Productivity in the Construction of the Victoria Square Tower B Apartment, Tangerang, Banten. Journal of Theoretical and Applied Civil Engineering, 25(2),103-112.
https://doi.org/10.5614/jts.2018.25.2.3 Rochmanhadi (1992) Heavy Equipment and Its Use, Jakarta 14 September 1998 : Foundation for Public Works Publishing Agency.
Joseph E. Bowles, PESE (1991) Analysis_and_Design_Foundations_volumes
_2_bowles. Jakarta : Erlangga.
Rostiyanti, SF (2008). Heavy Equipment For Construction Projects. Jakarta: Rineka Cipta .
Sardjono, HS, (1988) Pile Foundation (for universities and the public) volume 1, Surabaya: Sinar Wijaya.
DOI: https://doi.org/10.20527/crc.v6i1.5785
Refbacks
- There are currently no refbacks.
Copyright (c) 2022 Abnu Azhar, Eliatun Eliatun
This work is licensed under a Creative Commons Attribution 4.0 International License.
Indexed By:
GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0