STUDY OF PROJECT TIME AND COST PERFORMANCE USING THE EARNED VALUE MANAGEMENT METHOD ON THE ENVIRONMENTAL ROAD IMPROVEMENT PROJECT IN TANIPAH VILLAGE, MANDASTANA DISTRICT

Siti Salsabila, Abdul Karim, Humaira Afrila

Abstract


One of the methods used in controlling project time and costs is the earned value concept method. Earned value is a concept of calculating the cost budget by the work that has been completed. Where performance is measured is work completed at a certain time, which is assessed based on the amount of budget available on the project. For this reason, it can later be known the relationship between the physical progress achieved and the budget that has been spent.

In this study, the object of research used was the Tanipah Village Environmental Road Improvement project, Mandastana District, and used existing data, namely general project data, contract value, schedule, and weekly reports. This study uses project performance analysis based on time and cost using the Earned Value Management method.

The results of the data analysis obtained were that there was a delay in project work in week 1 and week 2, but scheduling performance improved so that in the following week there were no more delays and the project was completed on time. In terms of costs, in week 1 to week 7 the costs incurred exceeded the budget but in week 8 cost performance improved and in the last week the profit obtained amounted to Rp. 40,207,776.

 

Keywords: Earned Value, Cost, Time

Full Text:

PDF

References


Araszkiewicz, K., Bochenek, M. 2019. Control Of Construction Projects Using The Earned Value Method – Case Study. Journal of Open Engineering (1): 186-195

Ariana, IKA, Lestari, DA, & Nasional, UP (2023). Performance Analysis of Gatak SPAM Optimization Project Sukoharjo Regency using the Earned Value Method Performance Analysis of Gatak SPAM Optimization Project Sukoharjo Regency using the Earned Value Method How to Cite : (Salilama, 2016). Based on Regulations. 6(1), 87–102.

Ayu, I., Widhiawati, R., Diputra, GA, Gede, I., & Pradipta, P. (2014). Analysis of Contractor Profits With a Variety of Payment Systems (Case Study: Project for Improving the Structure of the Choker Road - National City Boundary) Analysis of Cash Flow With a Variety of Payment Systems To Contractors Benefit (Case Study: the Structure of Road Impr. Scientific Journal of Civil Engineering, 18 (2).

Judge, A. (2023). The Effect of Inflation and Interest Rates on Economic Growth in Indonesia. Economics, Finance, Investment and Sharia (EQUITY), 4(4), 1283–1291.

Hidayat, B., & Syahra, RA (2023). Identify the Level of Use of Daily Reports in Construction Projects. Building Journal: Construction & Design, 1(1), 1–10.

Imam Munandar, M., & Multi Rezeki, I. (2017). Construction Management of the Sutan Raja Guest House Development Project, Cirebon City. Construction Journal, VI(2), 165.

Laksono, T.D. (2007). Productivity on construction projects. Theodolite, 8(2), 11–18.

Langlang, H., Putra, B., & Simanjuntak, MRA (2021). Study of Time Control Factors in Multi-Storey Buildings at the Indonesian International Islamic University Campus Project. Proceedings of CEEDRiMS 2021 Technological Innovation and Renewable Materials Towards Disaster-Safe and Environmentally Friendly Infrastructure, 978-602-361-385–4, 255–261.

Magaline, HP, Haryono, AJ, & Andi. (2015). Survey of overhead costs and the factors that influence them. Survey of Overhead Costs and Factors That Influence Them, 1–8.

Mahapatni, IAPS (2019). Construction Project Planning and Control Methods. In UNHI Press.

Maya Sari, H., Hendriyani, I., & Ersa Widyaningrum, A. (2021). Earned Value Analysis on the BPN Office Archives Building Construction Project. TRANSUKMA Civil Engineering Scientific Journal, 3(2), 154–167.

Rantung, AHP, Sompie, BF, & Mandagi, RJM (2014). Cost and Schedule Control Analysis at the Construction Implementation Stage with "Earned Value Analysis". Media Engineering Scientific Journal, Civil Engineering, Sam Ratulangi University, Manado, 4(3), 190–203.

Studi, P., Civil, T., Engineering, F., & Petra, UK (2023). USE OF METAHEURISTIC ALGORITHM FOR FINANCE OPTIMIZATION-. 8(2).

Sulistia, D., & Agustina, ID (2023). Project Scheduling Using an S-Curve in Housing Development in Bekasi City. Al Ulum Journal LPPM Al Washliyah University Medan, 11(2), 100–106.

Triana, D., & Oktavianto, WO (2013). The Relevance of Civil Engineering Contractor Qualifications on the Quality of Construction Project Work in Banten Province. Foundations: Journal of Civil Engineering, 2(2), 182–190.

Wirahman, L., Warka, IGP, & Apriliana, A. (2015). The Influence of Payment Systems on Optimal Cash Flow in the Praya District Court Building Construction Project. Civil Spectrum, 2(2), 145–157.

Yuliana, C., Hapsari K., R., & Agustina, R. (2019). Integrated Cost and Time Performance Analysis with the Value of Results Concept in Construction Projects in Swamp Land. Journal of Civil Engineering Studies, 4(2), 176–183.




DOI: https://doi.org/10.20527/crc.v8i2.13440

Refbacks

  • There are currently no refbacks.


Copyright (c) 2024 Siti Salsabila, Abdul Karim, Humaira Afrila



Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License

joomla
statistics View My Stats

Indexed By:

 

GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0