ANALYSIS OF HEAVY EQUIPMENT PRODUCTIVITY IN THE PAVING WORK OF LASTON LAPIS WEAR (AC-WC) ROAD IN THE BANJARMASIN-MARTAPURA ROAD RECONSTRUCTION PROJECT SECTION II
Abstract
The reconstruction of the Banjarmasin-Martapura Road Section II is carried out to meet the community's needs for better transportation access. In this project, the role of heavy equipment is very important to support the efficiency and effectiveness of the project. This study aims to analyze the output level of heavy equipment based on theory and field conditions and identify factors that affect productivity in Laston Lapis Wear (AC-WC) road paving work.
The method applied in the analysis of heavy equipment production capacity is the Time Study Method. This method is used to calculate the standard time of work by collecting data on the amount of time it takes to complete a task.
The results of the study show that the production capacity of heavy equipment based on theory reaches 301.06 tons/day and the duration of work is 5 (five) days with the number of heavy equipment Asphalt Sprayer as many as 1 tool, Dump Truck as many as 20 tools, Asphalt Finisher as many as 1 tool, Tandem Roller as many as 1 tool, and Pneumatic Tire Roller a total of 1 tool. Meanwhile, based on the analysis carried out in the field, it was found that the productivity of all heavy equipment was 143 tons/day and the duration of work was 11 (eleven) working days with the number of heavy equipment Asphalt Sprayer as many as 1 tool, Dump Truck as many as 26 tools, Asphalt Finisher as many as 1 tool, Tandem Roller as many as 1 tool, and Pneumatic Tire Roller a total of 1 tool. The aspects that affect the performance of heavy equipment in this study are material factors, field, heavy equipment conditions, weather and time management.
Full Text:
PDFReferences
Akbar, F., Yamali, F. R., & Dwiretnani, A. (2021). Analysis of the Use and Productivity of Heavy Equipment in the Improvement of the Simpang Pauh-Air Hitam Road Section of Jambi Province. Journal of Civil Talent, 4(2), 114-119.
Aris, M., Pramanda, H., Kurniasari, F. D., & Ariansyah, D. (2023). Analysis of Productivity and Effectiveness of Heavy Equipment in the Work of Improving Irrigation Roads in Kr. Jreu Kec. Journal of Planning and Research in Civil Engineering, 2(1), 127-134.
Arsyad, R. (2021). Analysis of Heavy Equipment Productivity in the Pekanbaru-Padang Section VI Pekanbaru-Bangkinang Toll Road Construction Project (Doctoral dissertation, Riau Islamic University).
Bina Marga. (2010). General Specification 2010 (fix 2)", National Road Implementation Center V, Yogyakarta ; Directorate General of Highways, Department of Public Works.
Handayani, E., & Akbar, F. (2020). Study on the Efficiency of Heavy Equipment Productivity in Road Projects (Case Study: Mendalo Darat Road Section (Sp. Tiga)-Bts. Jambi City). Journal of Civronlit Unbari, 5(1), 16-22.
Indriani, F. (2023). Analysis of Heavy Equipment Productivity in Grained Pavement Work on the Handil Maluka Road Handling Project – Harapan Beach, Bumi Makmur District. Lambung Mangkurat University
Regulation of the Minister of Public Works and Public Housing Number 8 of 2023 concerning Guidelines for the Preparation of Construction Work Cost Estimates in the Field of Public Works and Public Housing
Prasetya, R. T., Yulianto, T., Nugroho, M. W., & Sundari, T. (2023). Time and Cost Analysis Based on Field Productivity Reference Using the Actual Cost Estimation Method. Journal of Engineering Research Cluster, 2(2), 11-20.
Prima, G. R., & Hafudiansyah, E. (2022). Heavy Equipment Productivity in Toll Road Project Work (Case Study: Pematang Panggang Kayu Agung Toll Road Section 2, Ogan Komering Ilir, South Sumatra). Acceleration: Scientific Journal of Civil Engineering, 3(2).
Purwanto, T., Wiranto, P., & Lukman, H. (2016). Heavy Equipment Productivity in the Construction of the Laratlamdesar Road Section, Maluku Province. Pakuan University Student Online Journal, 1(1).
Sihasale, H., Leuhery, L., & Titaley, H. D. (2023). Analysis of heavy equipment productivity in the construction of the Pattimura University Marina Center phase II in Hila Village. Journal Agregate, 2(2), 186-195.
Wardani, P. I. K., Ratih, S. Y., & Primantari, L. (2022). Productivity Analysis of Excavator and Dump Truck Heavy Equipment (Case Study of the Manahan Indoor Building Construction Project in Surakarta City). World Communication Media of Civil Sciences, 4(2), 46-51.
Zaoqi, A., Hasyim, H., & Warka, I. G. P. (2022). Evaluation of Heavy Equipment Productivity and Efficiency in Earthworks of Runway Extension Project at Lombok International Airport. Ganec Swara, 16(2), 1627-1636.
DOI: https://doi.org/10.20527/crc.v9i1.14686
Refbacks
- There are currently no refbacks.
Copyright (c) 2025 Ronna Sabilla Putri, Candra Yuliana, Aulia Isramaulana

This work is licensed under a Creative Commons Attribution 4.0 International License.
Indexed By:
GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0