RISK ANALYSIS ON THE IMPLEMENTATION OF THE CONSTRUCTION PROJECT OF THE HIGH PROSECUTOR'S OFFICE OF SOUTH KALIMANTAN PROVINCE (CONTINUED)

Irwina Sari Verdiyani, Abdul Karim, Muhammad Alfian Noor

Abstract


The change in the status of the capital city of South Kalimantan province has implications for the development of urban infrastructure. Various construction works are being carried out, such as the construction of buildings, roads, and bridges. In the implementation of a construction project, of course, there is never a risk that can hinder the implementation process wherever the project is carried out. For example, the South Kalimantan Provincial High Prosecutor's Office (Continued) project is one of the medium-risk projects.

The method used for this risk analysis is to use a quantitative research method with validity and reliability tests. Then analyze the Probability and Impact  data using the Severity Index calculation, which further determines the level of risk with the Matrix Probability and Impact. Then categorize these risk variables into risk acceptance scales in order to obtain the dominant risk variables that occur in the project.

The results of the research from the risk analysis on the Implementation of the South Kalimantan Provincial High Prosecutor's Office Development Project (Continued) obtained 15 valid risk variables. There were 11 dominant risk variables with medium categories  and 3 risks with high categories  that affected the project

Keywords: Risk, Risk Analysis, Building, Severity Index

Full Text:

PDF PDF

References


Afiq, M. (2021). Risk Management in the Construction Project of the UIN Walisongo Student Dormitory Building in 2021. Acceleration: Scientific Journal of Civil Engineering, 3(1), 70–80.

Asnuddin, S., Tjakra, J., & Sibi, M. (2018). The application of construction management at the project controlling stage. (Case Study: Laboratory Building, Faculty of Engineering, SAM Ratulangi University, Manado). Static Civil Journal, 6(11), 895–906.

Dewantoro, B. S., & Mardiyanto, A. (2019). Work Risk Management in the Case Study of the Kuto River Bridge. University of Semarang.

Karim, A. (2020). Risk Analysis of the Development of Basirih Landfill Incenerator Infrastructure in Banjarmasin City. Thesis.

Karim, A. (2023). Risk Analysis of Housing Development on Jl Golf, Liang Anggang District, Banjarbaru City (Case Study: PT Borneo Group Housing). Journal of Sustainable Technology, 12(1), 1-9.

Kiswati, S., & Chasanah, U. (2020). Project Management Planning in Improving the Effectiveness of Human Resource Performance in Semarang, Central Java. Journal of Neo Teknika, 6(1).

Labombang, M. (2011). Risk Management in Construction Projects. SMARTek Journal, 9(1), 39-46.

Lestari, I. G. A. A. I., Pradnyadari, N. L. M. A. M., & Anditha, I. K. D. A. (2024). Analysis and Mitigation of Safety Risks and Work Accidents in the Bali Intercontinental Grand Ballroom Development Project. Journal of Ganec Swara, 18(1), 419-426.

Muhammad, M. A. (2024). Construction Risk Analysis in the Implementation of the Banjarmasin Zero Kilometer Monument Construction Project. (Thesis, Faculty of Engineering, Lambung Mangkurat University: Banjarbaru).

Nurlela, & Suprapto, H. (2014). Identification and Analysis of Risk Management in Multi-storey Building Infrastructure Development Projects. Journal of Construction Design , 13(2), 114–124.

Pindonta Ginting, D. S., & Pontan, D. (2021). Identify the factors that affect the delay of the toll road construction project. Proceedings of the Young Intellectual Seminar #5, 2(2), 153-161.

Praniti, I. A., Putri, T., Norken, I. N., & Rai Adnyana, I. B. (2016). Risk Management in the Cost Estimation Process for a High-rise Building Construction Project in Denpasar City. Jurnal Spektran (Vol. 4, Number 2).

Ranjed, Y., Pingkan, P., Pratasis, A. K., & Mangare, J. B. (2017). Analysis of Factors Affecting Delays in Road Projects in (North Sulawesi Province). Static Civil Journal, 5(7), 451–464.

Rodhi, N. N., Pujidya Aryani, D., Yanuar, A., & Riadi, P. (2023). Analysis of Time and Cost Control of Construction Projects with the PERT Method (Projecct Evalution And Review Technique). SEMSINA 2023, 4 No. 2, 181–191.

Said, H. S., Khotimah, C., Ardiansyah, D., & Khadrinur, H. (2023). Validity and Reliability Test: Accounting Students' Understanding of Accounting For Business Courses or Introduction to Accounting (Study on S1 Accounting Students at Telkom University for the 2022/2023 Academic Year). Journal of Economics and Accounting Publications, 3(2).

Suwinardi. (2016). Project Risk Management. ORBITH, 12(3), 145-151.

Tjakra, J., & Sangari, F. (2011). Risk Analysis on Residential Construction Projects in Manado City. Scientific Journal of MEDIA ENGINEERING (Vol. 1, Number 1).

Wardhana, A. (2021). Risk Identification and Measurement. https://www.researchgate.net/publication/358138081




DOI: https://doi.org/10.20527/crc.v9i2.14839

Refbacks

  • There are currently no refbacks.


Copyright (c) 2025 Irwina Sari Verdiyani, Abdul Karim



Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License. 

joomla
statistics View My Stats

Indexed By:

 

GOOGLE SCHOLAR : Kutipan = 2, H-index = 1, i10-index = 0